CONFIRMING COMPLETION OF RAW LAND ASSESSMENT AND COMPENSATION UNDER TRANSMISSION LINE 500 kV OF JAWA-1 CCPP 1760 MW.
The object of the valuation is the property in the free space along the SUTET line from Java-1 PLTGU with a capacity of + 1,760 MW to an 8 Ha substation in Cikarang Utara sub-district, Bekasi Regency. Route Length: ± 52 km, Free Space Area: ± 34 m x 52 km = ± 160 Ha, Amount of Tower: ± 116 Tower, Amount Plot of Land: ± 1,377 Plot of Land, Track Area: Karawang District and Bekasi District West Java.